fbpx
Call
Enquire
Book an Appointment
1300 837 226 | 11am – 5pm Saturday to Wednesday New Opening hours: Open 7 Days, 11am - 5pm | Builder Hub
hero-june_
June 25,2020

June Construction Update

The team at Verdant Hill are delighted to deliver the June 2020 Construction Update, detailing the status of all works currently happening onsite.

We are also pleased to present our latest video update. Hear about construction updates and what’s happening within the development in 2020.

Landscape and Bridge Works update

Thanks to the recent wet weather, our street trees have really taken off in Stages 1 to 4 – they are looking lush and very happy!

The planting for stages 5 and 6 will commence in July 2020, and Stage 7 planting will be rolled out once the onsite civil works are complete.

The Park

The finishing touches are being made to the Clementine Blvd Park. This park has something for everyone with the skate-park elements, play equipment, BBQ and the picnic shelter all installed.

Fitness equipment has been located and designed to link in with the Dry Creek shared path trail for those fitness fanatics.

Florian Living Estate Manager - Abhishek Seth

The park will be open for use from July 2020.

The Dry Creek Plan has been approved by Council and the landscape enhancement for this area will commence by the end of 2020.

The Neighbourhood 2 (Cardinal Fields) landscape plan is also approved and works will be rolled out as stages are completed.

Rosso Drive Bridge Construction

Works are nearing completion for the bridge with rock beaching and painting yet to be completed.

Florian Living Estate Manager - Abhishek Seth

The bridge is a real feature of the estate and highlights the large open green space that Verdant Hill has to offer.

Civil Works

Dohertys Road – Stages 3 & 7 Intersections

Works are nearing completion on Dohertys Road with electrical/communications, kerb and footpath, final layer of asphalt and topsoiling yet to be completed.

We forecast that construction will be completed by mid-July 2020 with title registration by mid-September 2020.

Stage 8

Works are nearing completion for Stage 8 with electrical/communications, footpath, asphalt and topsoiling yet to be completed.

We forecast that construction will be completed by late July 2020 and title registration by early October 2020.

Stage 9

Works are nearing completion for Stage 9 with the final layer of asphalt and topsoiling yet to be completed.

We forecast that construction will be completed by mid-June 2020 with title registration by early October 2020.

Stage 10

Works are nearing completion for Stage 10 with asphalt and topsoiling yet to be completed.

We forecast that construction will be completed by late July 2020 with title registration by the end of October 2020.

If you would like to find out more about the Verdant Hill community and hear about our available land lots for sale or home & land packages, enquire today or call 1300 837 226.