Construction Update: Tangerine Creek Comes to Life

Construction Update: Tangerine Creek Comes to Life

Civil works at Verdant Hill's Tangerine Creek began in July and have been progressing smoothly over the past three months. An aerial view of the estate shows the exciting changes that have been taking place on the ground in each stage of the inaugural village.

Levels of completion for earthwork & sewer lines, drainage, gas & water, electrical and Opticom vary for each stage.


Stage One
100% complete:
 Earthwork & sewer line
95% complete:
 Drainage
25% complete:
 Gas & water
In progress:
 Electrical & Opticom (internet) conduit installation
Stage Two
100% complete:
 Earthwork
90% complete:
 Sewer line
90% complete:
 Drainage
In progress:
 Gas & water
Stage Three
85% complete:
 Earthwork
15% complete:
 Sewer line
In progress:
 Drainage
Stage Four
85% complete:
 Earthwork
100% complete:
 Sewer line
In progress:
 Drainage

These exciting developments are just the beginning. Stay up-to-date on these changes and more as Tangerine Creek continues to take shape over the coming months by following the Verdant Hill Facebook page.